News from the progress of construction works
- Construction chronicle
- |
- 4 March 2022
We are coming back to you with a fresh dose of news about the progress of work on the construction of the Bliskie Piaseczno estate. The most important news for today – everything is going according to the schedule. To sum up – the progress of construction works is very dynamic.
We have already completed all the foundations and walls of the ground floor and the first floor, and the ceiling above the ground floor has been completed.
In building A, the first floor ceiling has also been constructed. Walls and columns at the L02 level are also being constructed. But that’s not the end.
We have finished the reinforced concrete structure of level 2. Additionally, vertical elements, i.e. columns and walls in building A and 80% of vertical elements in building B have been made. Thus, we are moving on smoothly to level 3 in building A, where we have laid the ceiling. In the same building, we have also erected the structural columns and walls at level 4 and started construction of the flat roof. It is worth emphasizing that we have started the construction of partition walls in service premises.
Looking at the dynamics of the work, we feel that we are getting closer and closer to reaching the roof!